Step 3
The delivery
After the machine was tested during a FAT, it was delivered and installed at the customer’s site, after which the packaging line was commissioned. The limited installation space was the main factor that made this project non-standard. The equipment had to be adapted to the physical constraints of the environment. At the same time, the different bag sizes had to be configured correctly, and the existing palletizer had to be adjusted to the new setup.
This combination of new and existing components made proper system integration essential: hopper, weighing, filling, closing, flattening, conveying, and palletizing all had to function once again as one continuous packaging process.